Had to install some new mains tails for a small C/U replacement. The new mains tails come off a 3phase enclosure bus bar system. It's pretty Jurassic by the look of it!
I understand the testing process for the new board and I understand how to test the tails, however, I'm not sure on how to test some of the other requirements.
The busbar enclosure is fed from another DB which has a main rcd switch. I cannot test this main rcd switch as I cannot loose power to the building. On the test schedule the method of fault protection would be ADS but putting no RCD trip times on the sheet would be wrong?
Also, do the tails need a separate test sheet with them being from a separate enclosure?
Thanks
I understand the testing process for the new board and I understand how to test the tails, however, I'm not sure on how to test some of the other requirements.
The busbar enclosure is fed from another DB which has a main rcd switch. I cannot test this main rcd switch as I cannot loose power to the building. On the test schedule the method of fault protection would be ADS but putting no RCD trip times on the sheet would be wrong?
Also, do the tails need a separate test sheet with them being from a separate enclosure?
Thanks