Quite a few of our clients have large, old, high heat load buildings.
So having the EPC done at the correct time is critical to get the right RHI payments.
If the building has already or can't have cavity wall insulation and has 250mm of Loft insulation (or can't have it done), then the EPC as taken at that time will determine the Domestic RHI payments.
Well one of our clients had a heat load of 100,000 kWh and 32kW, and although we could easily have put in a biomass boiler to cope, he wanted to insulate the property, so the concept is: Solid wall insulation, double glazing and additional roof insulation, net effect a building that meets 2014 building regs, and a heat load of 32,000kWh and 10kW - easily doable with a GSHP. the big question was though, if we designed a system to meet 100% of the new load based on the MCS, even though now 1/3 of the EPC figures would they still pay in full?
Note: the cost of the improvements plus the GSHP is actually signifacntly higher that the cost it would have been to install the large biomass boiler. This wasn't about saving the initial capital cost, it was to reduce the on-going heating costs as much as possible.
As we know if the MCS calcs come out higher that the EPC, they are still only paying the EPC, well in this case it is lower, and after the improvements a lot lower, however the client wanted re-assurance that he would still be eleigible for the full RHI - the alternative would have been to install a now massively oversized biomass boiler and large buffer tank to meet only 1/3 of the old load.
Good news - Ofgem aren't worried about the MCS load calcs, so long as the system is designed to meet what the MCS calc say, they'll pay. - Here's ther actual response.:
My only concern is a few installers that may undersize systems to keep their costs down, and increase their profits, whislt effectively short changing the clinet, or delivering a system that doesn't meet the actual loads, and with 2 mild winters so for, they would have 'got away with it' to date. - There again they are probably already doing that anyway
Hope that helps some of you guys out there
So having the EPC done at the correct time is critical to get the right RHI payments.
If the building has already or can't have cavity wall insulation and has 250mm of Loft insulation (or can't have it done), then the EPC as taken at that time will determine the Domestic RHI payments.
Well one of our clients had a heat load of 100,000 kWh and 32kW, and although we could easily have put in a biomass boiler to cope, he wanted to insulate the property, so the concept is: Solid wall insulation, double glazing and additional roof insulation, net effect a building that meets 2014 building regs, and a heat load of 32,000kWh and 10kW - easily doable with a GSHP. the big question was though, if we designed a system to meet 100% of the new load based on the MCS, even though now 1/3 of the EPC figures would they still pay in full?
Note: the cost of the improvements plus the GSHP is actually signifacntly higher that the cost it would have been to install the large biomass boiler. This wasn't about saving the initial capital cost, it was to reduce the on-going heating costs as much as possible.
As we know if the MCS calcs come out higher that the EPC, they are still only paying the EPC, well in this case it is lower, and after the improvements a lot lower, however the client wanted re-assurance that he would still be eleigible for the full RHI - the alternative would have been to install a now massively oversized biomass boiler and large buffer tank to meet only 1/3 of the old load.
Good news - Ofgem aren't worried about the MCS load calcs, so long as the system is designed to meet what the MCS calc say, they'll pay. - Here's ther actual response.:
As long as the information on the MCS Database shows that the amount of heat provided by the system matches the property’s heat demand then it would not require metering. Payments for the Domestic RHI are based on the EPC regardless of any discrepancies between the heat load listed on the MCS Certificate so this would not be a reason an application was flagged for metering.
My only concern is a few installers that may undersize systems to keep their costs down, and increase their profits, whislt effectively short changing the clinet, or delivering a system that doesn't meet the actual loads, and with 2 mild winters so for, they would have 'got away with it' to date. - There again they are probably already doing that anyway
Hope that helps some of you guys out there