timo
Quoting for a job. Need to install a 1 way cu to feed shower as the exising is full and old none rcd unit etc.
noticed that the C.U is 16mm tails with only 6mm main earth. Do i need to alter this or just make sure my new 1 way is 16 with 25mm tails from splitter block.
noticed that the C.U is 16mm tails with only 6mm main earth. Do i need to alter this or just make sure my new 1 way is 16 with 25mm tails from splitter block.