Just done a PIR today on a first floor flat. Just want a few opinions on codings for a couple of issues i noted.
Firstly, none of the sockets have 30mA RCD protection. Being a first floor flat the sockets are very unlikely to be used to feed equipment outside so the requirements of the 16th Edition (the edition it was wired to at a guess) would have been met so would you code this as a 4 or would you lean more towards the current regs and give it a 2?
Similarly none of the bathroom supplies have any RCD protection. Supplementary bonding is present and correct so would you give it a code 2 or 4.
Finally, (not a coding query this time) the flat is fed from the incoming main in the shop below. I was able to access the shop first thing this morning and got a quick look at the meters etc so was able to fill in the supply characteristics however i had to put limitations on certain parts. This included Ze and PSC due to not being allowed to isolate the supply (shared supply with shop which was open at the time) and i wasn't able to test the submain to the flat as the shop keeper left very early and closed up without my knowledge. The tests on the submain at the flat CU came back good so i'm not overly worried and have plenty of remedial work to carry out so would you endeavour to get all the other testing (as far as practically possible) done on the return visit.
Firstly, none of the sockets have 30mA RCD protection. Being a first floor flat the sockets are very unlikely to be used to feed equipment outside so the requirements of the 16th Edition (the edition it was wired to at a guess) would have been met so would you code this as a 4 or would you lean more towards the current regs and give it a 2?
Similarly none of the bathroom supplies have any RCD protection. Supplementary bonding is present and correct so would you give it a code 2 or 4.
Finally, (not a coding query this time) the flat is fed from the incoming main in the shop below. I was able to access the shop first thing this morning and got a quick look at the meters etc so was able to fill in the supply characteristics however i had to put limitations on certain parts. This included Ze and PSC due to not being allowed to isolate the supply (shared supply with shop which was open at the time) and i wasn't able to test the submain to the flat as the shop keeper left very early and closed up without my knowledge. The tests on the submain at the flat CU came back good so i'm not overly worried and have plenty of remedial work to carry out so would you endeavour to get all the other testing (as far as practically possible) done on the return visit.