KevinS

Hi,
ive been tasked with writing a 'standard operation sheet' for plumbers to replace electric showers safely.

at the moment they are replacing showers with no test gear, then the electrician is following behind doing a Zs

my concern is; they turn it off at the dp switch and remove the shower, I am not happy that it is dead when they turn if off as they have no method of checking. There may be a fault on the dp switch and they would not know

is this an acceptable procedure
remove cover of shower.
turn shower on by double pole switch,
VOLTSTICK (yes I know) will indicate,
if volt stick does NOT indicate, stop and wait for advice off an electrician
turn off by dp switch, VOLTSTICK will stop indicating,
if VOLTSTICK does not stop indicating, stop and wait for electrician
switch breaker off at board and proceed

i know what you are going to say, but the company won't pay for test gear for 20+ plumbers, hence the VOLTSTICK idea.

is this classed as safe enough, it's safer than what's happening now,
cheers
 
I suggest reading GS 38 on to find out what a approved voltage tester is. The re read your post and see if you can see what is wrong with your post.

I can see what's wrong with it, I did mention turning off dp switch and the breaker, I also did mention 'can of worms'.
at the moment they are taking them out with no testing whatsoever
 
tell your tight-arsed employers to pay for a spark to carry out the electrical side of the job instead of penny pinching. let the plumbers stick to what they do best. ........ shifting sh**, slagging everbody off, drowning customers.
 
I can see what's wrong with it, I did mention turning off dp switch and the breaker, I also did mention 'can of worms'.
at the moment they are taking them out with no testing whatsoever


So basically your employer has realised the downfall of this and decided they need a scapegoat.

The reason safe isolation procedures suggest using a approved tester is for a reason, not because someone wants to be awkward. Think I may have PDF somewhere stating the correct procedure, I will post it up over the weekend so you can then give it to the plumbers safe in the knowledge it will be done correctly.
 
I can see what's wrong with it, I did mention turning off dp switch and the breaker, I also did mention 'can of worms'.
at the moment they are taking them out with no testing whatsoever

i really don't think you are going to the get the answer you are looking for, if they want a risk assessment/task sheet for this job I would just print them off the safe isolation procedure and them deal with it from there, that is honestly the only way to cover your arse without putting your self in the firing line
 
Couple of things don't worry about him connecting it up worry that he will upgrade it from a 7 to 9kw on a 3036 board as this seams to be the standard. Also isolation at the DP switch is a no no as domestic appliance guy got a shock from a cooker because the live connection was welded on at the switch.

One last point a voltage tester remember that they need to test between L-N then L-E then N-E because L-N would have been no good to the domestic appliance guy above
 
So a company big enough to employ 30 plumbers & vans wont spend ÂŁ30ish on a decent set of fluke volt probes for workers they are legally obliged to protect ?
i'll call a laywer and ambulance for you.
;-)
 
i really don't think you are going to the get the answer you are looking for, if they want a risk assessment/task sheet for this job I would just print them off the safe isolation procedure and them deal with it from there, that is honestly the only way to cover your arse without putting your self in the firing line

i have getting the answer I'm looking for - I'm not writing a procedure. Will let someone else do it, in a couple of weeks time he will have totally forgot that he asked me.
Cheers.
 
Is this the housing company with the Italian sounding name?

Untrained personnel isolating and working on unproven conductors is a death wish and no risk assessment or alternative method would satisfy a coroner at an inquest - Don't do it . Simple . They are looking for a scapegoat to aid production and cut costs , I doubt whether an electrician will ever "follow up"
 
a sligtht digression, but the last time i went to a shower that had been changed by a plumber, he'd found the 6mm cable was a tad short to reach the terminal block so he twisted and taped a bit of 2.5mm to the 6mm inside the shower. wondered why the shower wouldn't work a week later with his bodge all welded together and the 30A HRC fuse in the CU blown. muppet.
 
I can't see how this is going to work. Surely the plumbers would have to prove they're competent? at electrics ;)
How quickly behind the plumber does the electrician turn up to carry out the Zs measurement? 1 hour? 1 day? 1 week? Is the shower out of use until tested?
 

Reply to Plumbers replacing electric showers in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
373
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
939
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
1K

Similar threads

Try disconnecting the "central heating off" wire from terminal 2 and insulate it (eg Wago connector or choc block or similar) and tuck it out of...
2 3
Replies
32
Views
4K
  • Question
Hi Gingerrubix, The fact that your previous Tenant replaced a faulty socket plate which he used for an external EV, raises an eyebrow. Also your...
2
Replies
25
Views
3K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top