H
hodaire
just been to have a look at some electrical work on a house, underneath the main fuse there is a trafolite label saying PME system but the supply authority haven't supplied an earth, someone has clipped a 6mm cable down the side of the house and buried the end in the ground (stripped a foot of the end of the cable) ze is 300 ohms.
do i just need to get onto the supplier to provide an earth and if so why wasn't one provided in the first place
do i just need to get onto the supplier to provide an earth and if so why wasn't one provided in the first place