W
wattsup
2-bed
22 twin sockets
15 light points
3 ext fan (kitchen, wc, en suite
3 smoke detectors
1 burglar alarm (2 pir 2 door contacts)
rcbo protected dis board (8 ish circuits)
2 outside lights (bulkheads)
new build 30 x the above
there are 3-bed and 4-bed, guide shown is for two bed
3 bed add 3 twin sockets and one light point
4-bed add 6 twin sockets and two light points
My estimated time for two experienced sparks is 2-days first fix (no chopping all fast fix boxes), 2 days second fix.
Some will be able to do quicker, not bothered. Quality of work is a must and is the priority. So don't be put off by my estimated time, a day or two longer is not a problem
guide:
200 m 2.5 t&e
150 m 1.5 t&e
100 m brn & e
100 m blu sings
15 m10mm (cooker)
south yorks area
sockets/switches white plastic mk or similar(yet to be decided)
include, materials testing etc
willing to share 50/50 for the right person/s
Start date november (approx)
pm please
Further:
kitchen fan 150mm
wc fan 100mm run on with timer
en suite fan 100mm run on with timer
kitchen, lighting track with 4 x spots
outside lights 2 x oyster bulkhead/ round or similar
garage 1 x 5ft flu light.
(reliable client)
oops forgot
4 x tv points (for 2-bed) sky ready-- coax left in loft areas
The above is slightly over estimated by 3 x twin sockets, and 2 x lighting points, cable is slightly over estimated by 10%, so please don't add further.
ch is by plumbers, they will install, we will only connect at dis board
I estimate 2 days first fix and two days second fix for two experienced sparks. Some will be quicker. Do not be put off by my estimation, some guys are slow but good, some are quick and rough, I want good above all else, so a day or so longer would not bother me
22 twin sockets
15 light points
3 ext fan (kitchen, wc, en suite
3 smoke detectors
1 burglar alarm (2 pir 2 door contacts)
rcbo protected dis board (8 ish circuits)
2 outside lights (bulkheads)
new build 30 x the above
there are 3-bed and 4-bed, guide shown is for two bed
3 bed add 3 twin sockets and one light point
4-bed add 6 twin sockets and two light points
My estimated time for two experienced sparks is 2-days first fix (no chopping all fast fix boxes), 2 days second fix.
Some will be able to do quicker, not bothered. Quality of work is a must and is the priority. So don't be put off by my estimated time, a day or two longer is not a problem
guide:
200 m 2.5 t&e
150 m 1.5 t&e
100 m brn & e
100 m blu sings
15 m10mm (cooker)
south yorks area
sockets/switches white plastic mk or similar(yet to be decided)
include, materials testing etc
willing to share 50/50 for the right person/s
Start date november (approx)
pm please
Further:
kitchen fan 150mm
wc fan 100mm run on with timer
en suite fan 100mm run on with timer
kitchen, lighting track with 4 x spots
outside lights 2 x oyster bulkhead/ round or similar
garage 1 x 5ft flu light.
(reliable client)
oops forgot
4 x tv points (for 2-bed) sky ready-- coax left in loft areas
The above is slightly over estimated by 3 x twin sockets, and 2 x lighting points, cable is slightly over estimated by 10%, so please don't add further.
ch is by plumbers, they will install, we will only connect at dis board
I estimate 2 days first fix and two days second fix for two experienced sparks. Some will be quicker. Do not be put off by my estimation, some guys are slow but good, some are quick and rough, I want good above all else, so a day or so longer would not bother me
Last edited by a moderator: