F
forstal17
Hi,
I installed a PV system recently on a three phase installation. Each phase had its own inverter so effectively three single phase installations. Two of the inverters were to have 12 x 250watt panels connected, the third was to have 14x 250watt panels connected to it. Until that point all inverters I had worked on had two dc inputs, one for each string, on seperate MPP trackers but the inverters for this site were single input. Because of this i installed the strings in parallel (6+6, 6+6, and 7+7) to keep the voltage within the inverters range. So two strings connected in parrallel into adaptable box with one dc pair going back to the inverter, each sytem was done this way. Everything was fully commissioned - no problems. About two weeks after installation an error code appeared on one inverter indicating a "bus undervoltage". I returned to site, read the manual and the remedy was to reset and if it continued to contact the manufacturer (NEDAP inverter). Obviously i checked and looked at each system and couldn't see anything obvious. I reported this back to the MCS company that had instructed me to do the work. Anyway I should have seen the signs but they only paid for half the work I done for them. They have now told me that they got another electrician to go there and he found a string was connected reverse polarity (I have worked in telecoms dc for a long time and am very aware of this so find it hard to beleive) They also said they swapped the inverter anyway?? They ALSO said they found reverse polarity on a second string on a different inverter and so that system was operating at 50 %?? (I checked when I had went to fault find initial fault and two working systems had approx the same amount of generation, and everything seemed fine at time of commission). Any way my theory is that the DC isolators i was using had staggered inputs across the top numbered 1,3,5,7 and on the bottom 8,6,4,2 meaning pos input on position 1 (top left) out on position 2 (bottom right) I think the "electrician" has took the cover off and it "appears" to be incorrect as normally the isolator would be in on top left out on bottom left and so on. I have done the C&G course recently but haven't done many installs so would just like to clear up the following scenarios:
1. If one string was reverse polarity on an inverter with two inputs on seperate MPP trackers, what would be the likely generation (ie would it simply be around 50%) and would it cause further problems
2. If one string was reverse polarity when you had connected two strings in parrallel into an adaptable box, then took one pair of cables to an inverter with only one tracker, what would be the likely generation,
3. Has anyone used this type of staggered isolator before (32Amp 4 pole unsure of manufacturer)
I cant find anything in my notes that answers this but strongly believe they are trying to get out of paying the remainder of what they owe. I even gave them a 5 year warranty so there was no need to pay anyone else as i would have repaired it for free if it was incorrect!
I would really appreciate any firm answers on this as i want to go to them with absolute certainty that this was not the problem. Unfortunately i cannot just go to site to check for myself. Thanks in advance
I installed a PV system recently on a three phase installation. Each phase had its own inverter so effectively three single phase installations. Two of the inverters were to have 12 x 250watt panels connected, the third was to have 14x 250watt panels connected to it. Until that point all inverters I had worked on had two dc inputs, one for each string, on seperate MPP trackers but the inverters for this site were single input. Because of this i installed the strings in parallel (6+6, 6+6, and 7+7) to keep the voltage within the inverters range. So two strings connected in parrallel into adaptable box with one dc pair going back to the inverter, each sytem was done this way. Everything was fully commissioned - no problems. About two weeks after installation an error code appeared on one inverter indicating a "bus undervoltage". I returned to site, read the manual and the remedy was to reset and if it continued to contact the manufacturer (NEDAP inverter). Obviously i checked and looked at each system and couldn't see anything obvious. I reported this back to the MCS company that had instructed me to do the work. Anyway I should have seen the signs but they only paid for half the work I done for them. They have now told me that they got another electrician to go there and he found a string was connected reverse polarity (I have worked in telecoms dc for a long time and am very aware of this so find it hard to beleive) They also said they swapped the inverter anyway?? They ALSO said they found reverse polarity on a second string on a different inverter and so that system was operating at 50 %?? (I checked when I had went to fault find initial fault and two working systems had approx the same amount of generation, and everything seemed fine at time of commission). Any way my theory is that the DC isolators i was using had staggered inputs across the top numbered 1,3,5,7 and on the bottom 8,6,4,2 meaning pos input on position 1 (top left) out on position 2 (bottom right) I think the "electrician" has took the cover off and it "appears" to be incorrect as normally the isolator would be in on top left out on bottom left and so on. I have done the C&G course recently but haven't done many installs so would just like to clear up the following scenarios:
1. If one string was reverse polarity on an inverter with two inputs on seperate MPP trackers, what would be the likely generation (ie would it simply be around 50%) and would it cause further problems
2. If one string was reverse polarity when you had connected two strings in parrallel into an adaptable box, then took one pair of cables to an inverter with only one tracker, what would be the likely generation,
3. Has anyone used this type of staggered isolator before (32Amp 4 pole unsure of manufacturer)
I cant find anything in my notes that answers this but strongly believe they are trying to get out of paying the remainder of what they owe. I even gave them a 5 year warranty so there was no need to pay anyone else as i would have repaired it for free if it was incorrect!
I would really appreciate any firm answers on this as i want to go to them with absolute certainty that this was not the problem. Unfortunately i cannot just go to site to check for myself. Thanks in advance