i have a project at the planning stage at the moment. 100kw across 3ph. dno say that the infrastucture is not capable of feed back, and would need a costly upgrade.
however he says that we can still get the feed back tariff using the pv generated on site but using a controller other than the g59 to prevent feed back to the grid. if anyone could elaborate on this i would be thankful.