Hi

I've done a fuse board change on a piece of private land that has two static caravans on it. Main fuse board feeds to the two vans, two external plugs, and a wash house.

All hunkdory, except the wash house is fed by a two wire swa to the submain in the house, and staked down there. As I am only changing the main board (so all sub mains aren't included) I have just tested the feeds. As the wash house feed hasn't got an earth in the cable (the sheath is earthed), do I just do an R1R2 test using the sheath (although it is not being used as a CPC), or put it down as a limitation?

I'd be interested in your views.

Thanks all.
 
Yeah i agree probally worth putting a comment on the test sheet about the stake beign there aswell
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
R1+R2 query
Prefix
N/A
Forum
Periodic Inspection Reporting & Certification
Start date
Last reply date
Replies
5

Advert

Thread statistics

Created
Scooter,
Last reply from
kayeno,
Replies
5
Views
1,172

Advert

Back
Top