Hi all,
I just wanted to pick some brains ahead of having a chat with a potential customer.
Essentially it's a farm with a single phase supply, but an 11kVA 3 phase line a few hundred yards away. There are actually 3 farms clustered together, and I'm thinking it's likely that they're all fed from a different phase from a 3 phase transformer.
My query basically is around the issues with maximum SSEG sizing, and how much of this is related to whether the 3 phases are balanced or not. ie if all 3 phases have the same level of generation on them is this more likely to mean the DNO would allow a greater level of SSEG on all 3 phases than if an SSEG was only installed on a single phase.
Reason being that we should be able to fit 50kWp on the barn at this farm, but I can't see any way the DNO is likely to allow this. The other 2 farms though also look like they'd be suitable, so I was thinking it could be worth asking about the potential to do all 3 together, to see if it made any difference to the total allowed.
There's also the potential to ask about upgrading the transformer, which would be more cost effective if spread between the 3 farms.
I'll obviously be doing a G59 application, just wondering if anyone had any experience of anything similar / think I'm on to something / barking up the wrong tree?
I'm not thinking we're going to get anything like 50kW on a single phase, but was thinking it might push up what they allow from 10kW to 17kW per phase or something - I've vague recollections of a DNO engineer saying something along these lines at some stage.
I just wanted to pick some brains ahead of having a chat with a potential customer.
Essentially it's a farm with a single phase supply, but an 11kVA 3 phase line a few hundred yards away. There are actually 3 farms clustered together, and I'm thinking it's likely that they're all fed from a different phase from a 3 phase transformer.
My query basically is around the issues with maximum SSEG sizing, and how much of this is related to whether the 3 phases are balanced or not. ie if all 3 phases have the same level of generation on them is this more likely to mean the DNO would allow a greater level of SSEG on all 3 phases than if an SSEG was only installed on a single phase.
Reason being that we should be able to fit 50kWp on the barn at this farm, but I can't see any way the DNO is likely to allow this. The other 2 farms though also look like they'd be suitable, so I was thinking it could be worth asking about the potential to do all 3 together, to see if it made any difference to the total allowed.
There's also the potential to ask about upgrading the transformer, which would be more cost effective if spread between the 3 farms.
I'll obviously be doing a G59 application, just wondering if anyone had any experience of anything similar / think I'm on to something / barking up the wrong tree?
I'm not thinking we're going to get anything like 50kW on a single phase, but was thinking it might push up what they allow from 10kW to 17kW per phase or something - I've vague recollections of a DNO engineer saying something along these lines at some stage.