Relevant building or not? | on ElectriciansForums

Discuss Relevant building or not? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

S

solgen

Hi,

I have a 30kW project where panels are to be mounted on a warehouse style building that has no form of heating but has just had a 3 phase supply added to it for the purpose of running a large heat pump. The heat supplies two other buildings (main house and maids quarters) but they are on a separate single phase supply.

How would this situation be classified and how would the higher tariff be achieved?

Thank you
 
The key thing is - the rules:

3.41. FIT Licensees are required to check energy efficiency requirements for every solar PV installation with a DNC up to and including 50kW, including extensions, with the exception of stand-alone, with an Eligibility Date on or after 1 April 2012.

3.42. The energy efficiency requirement applies if a PV installation (or extension) with an Eligibility Date on or after 1 April 2012 is wired to provide electricity to one or more relevant buildings.

3.43. FIT Licensees are required to check whether the energy efficiency requirement applies and, if so, these installations are required to demonstrate that the building to which the solar PV is wired to provide electricity has achieved an Energy Performance Certificate (EPC) rating of level D or above in order to receive the higher tariff, provided the multi-installation tariff (see multi-installations tariff section) does not apply.

Applications from FIT Generators who do not have an EPC (including definition of a relevant building)
3.80. A ”relevant building” is defined in the SLCs and must be a roofed construction which has walls, and for which energy is used to condition the indoor climate. Examples of energy being used to condition the indoor climate include heating and cooling systems. If any aspect of this definition does not apply to a building to which the PV installation is wired to provide electricity to then the energy efficiency requirement does not apply.
3.81. A “relevant building” must also be a building in respect of which an EPC can be issued. If an EPC cannot be issued then the building is not a relevant building and the energy efficiency requirement does not apply. Under the Energy Performance of Buildings (EPB) Regulations some properties are exempt from the requirement for an EPC; however if a building can be assessed and receive an EPC then the energy efficiency requirement will apply under FIT legislation (irrespective of whether an EPB exemption applies or not).
3.82. It is the responsibility of the FIT Generator to prove that an EPC cannot be obtained for any building that the PV is wired to provide electricity to. One option to demonstrate this would be for the FIT Generator to provide a document from an EPC assessor which confirms that it was not possible to obtain an EPC on the building/s and to clearly state the reasons why.
3.83. A FIT Generator who claims, for any of the reasons outlined above, that a building to which the installation is wired to provide electricity is not a relevant building such that the energy efficiency requirement does not apply will be required to provide a declaration to that effect with their application. A copy of the declarations can be found in Appendix 5 and 6.
3.84. The evidence that the energy efficiency requirement does not apply and the corresponding declarations should be provided at the time of application. This will enable the FIT Licensee to confirm that at the time of the determination of an installation’s Eligibility Date the energy efficiency requirement did not apply
3.85. Failure to demonstrate that the energy efficiency requirement does not apply at the installations Eligibility Date will result in the FIT installation receiving the lower tariff.

Interestingpoints here:
3.80 - a) The climate of this building is not conditioned. (presumably it doesn't just have it's own supply it must have it's own MPAN)
and
b) The requirement for an EPC only relates to "a building to which the PV installation is wired to provide electricity to"

So long as they are separate supplies with separate MPAN's, then I would interpret that this building doesn't require an EPC, the same as if what was attached to it was a grain drier..
 
Last edited:
I have EPC done on all commercial buildings including grain dryers, Churches and Cold storage buildings. The cost to me is only £150.00, so for peace of mind, worth it.
 
Also where is the heat pump phsically located, if it is located at the other building, then it could be interpreted that the other building has an electrcity supply from this one....
 
The meter in the barn is supplying the heating to the other properties and so is supplying electricity to the other properties and so a domestic EPC from one of the other properties may be acceptable under 2.95/2.96 of the Feed-in Tariff: Guidance for renewable installations (Version 5) document.
 
@Matty just for your info, the latest version is 5.2 (paras 3.97, 3.98 would be the equivalent) the point is the system ISN'T "wired to provide electricity to" .....
 

Reply to Relevant building or not? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Sticky
  • Article
Wicked I've just actually looked through it and it's very smart. Some good stuff in it. There's a tile association company that do a magazine...
Replies
2
Views
303
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
284
  • Article
Hi everyone, Another weekend, another sale! Get ready for colder days with Haverland Radiators, combining efficiency with modern design. Keep...
Replies
0
Views
356

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top