Working on a RFC today and its had a stand alone RCD added previously which is installed outside of the 3036 fuse board.
When testing ring continuity and R1R2 would taking the conductors out of the RCD then joining them be the prefered method or taking 2 readings, one from the fuse board to the RCD then the other from the RCD out round the ring?
I know the values will be the same either way but just wanted to see how others would approach it.
When testing ring continuity and R1R2 would taking the conductors out of the RCD then joining them be the prefered method or taking 2 readings, one from the fuse board to the RCD then the other from the RCD out round the ring?
I know the values will be the same either way but just wanted to see how others would approach it.