Would you all agree with me that this is the correct way for 3ph Safe isolation as I advised my apprentice of this and he has been knocked back by C&G as insufficient.
Prove Tester on known source or proving unit
Prove installation is Live
Switch off installation
Prove Tester on known source or proving unit
L1-L2
L1-L3
L2-L3
L1-N
L2-N
L3-N
L1- EARTH
L2-EARTH
L3- EARTH
N-EARTH
Prove Tester on known source or proving unit
Lock off
Retain key
Hang signs
Cheers
Would you all agree with me that this is the correct way for 3ph Safe isolation as I advised my apprentice of this and he has been knocked back by C&G as insufficient.
Prove Tester on known source or proving unit
Prove installation is Live
Switch off installation
Prove Tester on known source or proving unit
L1-L2
L1-L3
L2-L3
L1-N
L2-N
L3-N
L1- EARTH
L2-EARTH
L3- EARTH
N-EARTH
Prove Tester on known source or proving unit
Lock off
Retain key
Hang signs
Cheers
Last edited by a moderator: