B
bullethead
My second post coming up and once again a 'hypothetical' that could become reality shortly...
Install a radial socket circuit in a garage supplied from a spare way in the consumer unit (RCD protected), all tests ok.
1. Presumably this requires a EIC and associated Schedule of Inspections?
2. Regarding the 'Presence of supplementary bonding conductors' box, would I be expected to go into the clients bathroom to check, or as it is not related to the work I carry out, do I put it as 'N/A'?
3. Assuming I check and find it is necessary but not there, what happens then... client only wanted some sockets in the garage!
Probably a dumb question to most of you but I'm on a steep experience gathering curve!
Install a radial socket circuit in a garage supplied from a spare way in the consumer unit (RCD protected), all tests ok.
1. Presumably this requires a EIC and associated Schedule of Inspections?
2. Regarding the 'Presence of supplementary bonding conductors' box, would I be expected to go into the clients bathroom to check, or as it is not related to the work I carry out, do I put it as 'N/A'?
3. Assuming I check and find it is necessary but not there, what happens then... client only wanted some sockets in the garage!
Probably a dumb question to most of you but I'm on a steep experience gathering curve!