Hi looking for friendly advice went to a property today, has a 32a breaker that feed downstairs sockets and upstairs socket. Now the cables are consist of ali multi braided I've advised that the they have a new downstairs ring and upstairs ring wired and old to be non existent now they require more breakers in the boad to future proof the house if any other circuit need adding. Now with changing the mains and adding two additional circuits I need to complete a electrical installation certificate my question is am I okay in setting limitations with the client and recording them on the cirt with regards to all other circuits I'll just been reconnecting them when doing the mains change.