Hi people,a theoretical question for you,if you was called to a house to fit a shower circuit & there was an old fusebox still in (re-wirable),after advising of updating this to a 17th edition cu,where would you stand with the regulations in fitting the shower circuit if they didn't want the cu changing at the minute(cost).Can you still go ahead by splitting the tails with a henley into a seperate small cu with a 30ma RCD so they can still have the shower circuit done (obviously the correct materials have been used & circuit tested after installation.Would i be right in saying this is the best way to go considering the situation
thanks in advance,jason