surveyed a job this afternoon.....well an `electrician`...lol....an electrician had been there already to feed a garage
(origin of supply is TN-S).....he`s gone and used a 2.5mm CSA
(why not a 4.0mm CSA i thought) ...but he`s bought a length thats now too short.. as he`s altered the run its taking without any due thought....lol...
told the customer i could joint it on a through box (surface mounted near the house C/U) onto a bit more armoured to get the length to go to the bottom of the C/U (metalclad)....or re-feed with a new armoured ......
then i got into the garage itself...to see what he`d done in there.....luckily enough theres enough length on the armoured feed in there to avoid joints....but theres bits of 1.5 flat to feed sockets (4 ov) in old colours.....1.0 flat for his lighting ..again old colours....and general untidiness of his work.....so i asked the chap if this guy had said anything to him about certification......response was the all to common....`he never mentioned anything about that`....hmm....
i gave him 2 prices...one to use the existing armoured.....the other to re-feed....either way the garage `install` that this joey has done will need re-doing (new colours & correct CSA)
so he`s gone with the cheaper option (well, theres a surprise..lol).....
start thursday mornin....sort it out....terminate, test and issue ticket....
surveyed a job this afternoon.....well an `electrician`...lol....an electrician had been there already to feed a garage
(origin of supply is TN-S).....he`s gone and used a 2.5mm CSA
(why not a 4.0mm CSA i thought) ...but he`s bought a length thats now too short.. as he`s altered the run its taking without any due thought....lol...
told the customer i could joint it on a through box (surface mounted near the house C/U) onto a bit more armoured to get the length to go to the bottom of the C/U (metalclad)....or re-feed with a new armoured ......
then i got into the garage itself...to see what he`d done in there.....luckily enough theres enough length on the armoured feed in there to avoid joints....but theres bits of 1.5 flat to feed sockets (4 ov) in old colours.....1.0 flat for his lighting ..again old colours....and general untidiness of his work.....so i asked the chap if this guy had said anything to him about certification......response was the all to common....`he never mentioned anything about that`....hmm....
i gave him 2 prices...one to use the existing armoured.....the other to re-feed....either way the garage `install` that this joey has done will need re-doing (new colours & correct CSA)
so he`s gone with the cheaper option (well, theres a surprise..lol).....
start thursday mornin....sort it out....terminate, test and issue ticket....