im in the process of pricing a small flat development (sheltered accommodation/safe house. type thing
It's a 2 storey mid terrace. Being converted to 6 bedroom with small en suites. Shared kitchen diner.
Initially I told the developer they need a 3 phase supply as electric showers and heating specified etc.
Since then they have fallen over with price getting said supply!
So now all hot water and heating will be from gas boiler etc.
So I have spencer the following
Supply is in cellar as per usual terrace 100a
12 way board
X6 32a feeds for each bedroom (only have 4 sockets and 3 low energy lights) mining board with rcbos
-kitchen ring
-oven
-hob
-kitchen lighting and landlords areas( hallway stairs)
-boiler supply
Just running it by you guys as a way of getting round the job spec.
Or should I insist on least another single phase supply.
I don't see it a load issue with the nature of the building use.
Any pointers much appreciated
It's a 2 storey mid terrace. Being converted to 6 bedroom with small en suites. Shared kitchen diner.
Initially I told the developer they need a 3 phase supply as electric showers and heating specified etc.
Since then they have fallen over with price getting said supply!
So now all hot water and heating will be from gas boiler etc.
So I have spencer the following
Supply is in cellar as per usual terrace 100a
12 way board
X6 32a feeds for each bedroom (only have 4 sockets and 3 low energy lights) mining board with rcbos
-kitchen ring
-oven
-hob
-kitchen lighting and landlords areas( hallway stairs)
-boiler supply
Just running it by you guys as a way of getting round the job spec.
Or should I insist on least another single phase supply.
I don't see it a load issue with the nature of the building use.
Any pointers much appreciated