Hi guys,
I have been asked to price up a job thats a little outside of what I generally do and im hoping to get some advice from you sparks who are more experienced in the design of an installation.
Iv got a block that an investor is converting to 24 studio flats, all electric, no gas.
3 floors, 8 flats per floor, and a 3 phase supply comprising of 3 x 300 amp main heads.
each flat will have
2 x 2 kw heaters
1 x 8.5kw shower
1 x 8.5kw water heater
And then the obvious general of course.
now im working out each flat with a maximum demand load of approx 20kw
approx 160kw per floor or 696amps. I know I have to take into consideration diversity, But even so this does seem way to high for the head to handle.
Thanks in advance for your opinions.
I have been asked to price up a job thats a little outside of what I generally do and im hoping to get some advice from you sparks who are more experienced in the design of an installation.
Iv got a block that an investor is converting to 24 studio flats, all electric, no gas.
3 floors, 8 flats per floor, and a 3 phase supply comprising of 3 x 300 amp main heads.
each flat will have
2 x 2 kw heaters
1 x 8.5kw shower
1 x 8.5kw water heater
And then the obvious general of course.
now im working out each flat with a maximum demand load of approx 20kw
approx 160kw per floor or 696amps. I know I have to take into consideration diversity, But even so this does seem way to high for the head to handle.
Thanks in advance for your opinions.