I am currently working through unit 307 Task C. All going fine except a bit stuck on this question -
Phase sequence is to be confirmed for the distribution boards and equipment during initial verification. State the 2 types of instrument used to check for correct phase sequence.
So we have a phase rotation tester as number 1.
As for number 2 i am a bit stuck. I know my voltage indicator can perform this test aswell but was wondering if i am missing something as this does not feel like the answer to me.
Thanks in advance for any help on this.
Phase sequence is to be confirmed for the distribution boards and equipment during initial verification. State the 2 types of instrument used to check for correct phase sequence.
So we have a phase rotation tester as number 1.
As for number 2 i am a bit stuck. I know my voltage indicator can perform this test aswell but was wondering if i am missing something as this does not feel like the answer to me.
Thanks in advance for any help on this.