when i measure Ze from a DB ( disconnecting main bonding) am i suppose to reconnect bonding b4 testing Zs on final circuits. on job 2day some Zs from sockets was lower than Ze. i put this down to parralell paths but am i doing it correctly??
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Discuss testing Zs and Ze in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net
when i measure Ze from a DB ( disconnecting main bonding) am i suppose to reconnect bonding b4 testing Zs on final circuits. on job 2day some Zs from sockets was lower than Ze. i put this down to parralell paths but am i doing it correctly??
Reply to testing Zs and Ze in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net