J
JulianC
Righty, since deciding to retrain as a spark it's amazing how many people come out of the woodwork with jobs that need doing. The situation with one elderly relative is this:
At one end of her kitchen, there is a single pendant light operated by a single switch. Apparently the light stopped working a while back (new lamp didn't cure it ) and said relative claims to have received 'a tingle' from the switch (take this with a pinch of salt to be honest). This is of course a simple fault to diagnose and fix. However, the house is fed from a BS3036 fuseboard with not an RCD in site. Obviously being a real-world house, the wiring is not in earthed metallic conduit or more than 50mm in the wall. Everything I have learned to date shouts at the need for RCD protection but if the relative won't pay for a board upgrade and just wants her kitchen light fixed, what are my options (from a regs. compliance standpoint)?
As I see it I can:
1. Replace lighting circuit fuse with RCBO - not possible as they don't exist to replace rewireable fuses as far as I can tell
2. Install a stand alone RCCB between meter and board - provides the necessary RCD protection but still at a cost that will not be attractive and will be refused. Risk of nuisance tripping to consider too.
3. Just fix the damned light and stop worrying - state the requirement to upgrade to RCD protection on the Minor Works cert. as a recommendation
4. Refuse the work - not an option
The sensible side of me says option 3 is OK as far as the legalities are concerned, as I will not be leaving the installation in a worse state of regs. compliance than prior to carrying out the work. However, by working on the lighting circuit I take on responsiblity for it's compliance with BS7671 do I not? Does 'reasonably practicable' come into this? After all, I can't force the customer into works they can't/won't have done.
I use the job above as an example but my question applies to any similar situation. Have looked around, including on these forums, and there seems to be no definitive answer.
Thank you.
At one end of her kitchen, there is a single pendant light operated by a single switch. Apparently the light stopped working a while back (new lamp didn't cure it ) and said relative claims to have received 'a tingle' from the switch (take this with a pinch of salt to be honest). This is of course a simple fault to diagnose and fix. However, the house is fed from a BS3036 fuseboard with not an RCD in site. Obviously being a real-world house, the wiring is not in earthed metallic conduit or more than 50mm in the wall. Everything I have learned to date shouts at the need for RCD protection but if the relative won't pay for a board upgrade and just wants her kitchen light fixed, what are my options (from a regs. compliance standpoint)?
As I see it I can:
1. Replace lighting circuit fuse with RCBO - not possible as they don't exist to replace rewireable fuses as far as I can tell
2. Install a stand alone RCCB between meter and board - provides the necessary RCD protection but still at a cost that will not be attractive and will be refused. Risk of nuisance tripping to consider too.
3. Just fix the damned light and stop worrying - state the requirement to upgrade to RCD protection on the Minor Works cert. as a recommendation
4. Refuse the work - not an option
The sensible side of me says option 3 is OK as far as the legalities are concerned, as I will not be leaving the installation in a worse state of regs. compliance than prior to carrying out the work. However, by working on the lighting circuit I take on responsiblity for it's compliance with BS7671 do I not? Does 'reasonably practicable' come into this? After all, I can't force the customer into works they can't/won't have done.
I use the job above as an example but my question applies to any similar situation. Have looked around, including on these forums, and there seems to be no definitive answer.
Thank you.