hello everyone! On a new installation (a poultry house) one circuit supplies a control panel, which controls fans(there are 29 over three rows all 3ph) a misting system(basicaly just a 3ph pump) and the heaters (6 all 1ph). should i be filling out a complete new form for this panel or is there some way i could record all the diffrent values on the original form?
 
you should fill in a different cert for any peice of the installation which comes from a new protective device.

Ie. a cert for the circuit that supplies your panel. a cert for the circuits from that point. if your mister is a self contained unit that contains a breaker for that pump, (ive used them before and the ones i used did) then you have to fill in cert for that also.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
three phase testing a circuit with a crontroll panel
Prefix
N/A
Forum
Periodic Inspection Reporting & Certification
Start date
Last reply date
Replies
1

Advert

Thread statistics

Created
woneye69,
Last reply from
johnboy6083,
Replies
1
Views
1,964

Advert

Back
Top