Hi,
Welcome to my domestic supply, the product of many electricians some qualified, some employed by builders over the years undoubtedly less so!
- can somebody please confirm if this is TN-S please (lead incoming cable)
Also, although I dont make a habit of looking at it - is this the correct way to do the earthing?
Looks like a just standard earth bonding strap (is that good enough?) and I thought this should go to the MET block not both ways to the MET and off to the CU directly. I guess it doesnt really matter impedance wise.
Warning - follow up question is about a garage
A long time back when the garage went up I was told to put a 4mm two core SWA over to the garage, which I duly did, but to be honest as the garage was only ever used as a store it never got wired up.
More recently as some other work was being done I put a much larger 16mm 3 core SWA feed over to the garage (only 1.2m from the house; total about 15m cable length to where the garage CU is planned) in anticipation of purchase of an EV (32A charge).
I assume even with the garage this close is is best to TT it, not export the earth.
Did wonder though whether to use the 4mm for the CU in the garage and just have the EV charge point direct, probably off a small CU added in the houseas the current board is already full (and yes the tails going to need upgrading fro m16mm to 25mm for those of you with sharp eyes)
Thoughts appreciated please.
Welcome to my domestic supply, the product of many electricians some qualified, some employed by builders over the years undoubtedly less so!
- can somebody please confirm if this is TN-S please (lead incoming cable)
Also, although I dont make a habit of looking at it - is this the correct way to do the earthing?
Looks like a just standard earth bonding strap (is that good enough?) and I thought this should go to the MET block not both ways to the MET and off to the CU directly. I guess it doesnt really matter impedance wise.
Warning - follow up question is about a garage
A long time back when the garage went up I was told to put a 4mm two core SWA over to the garage, which I duly did, but to be honest as the garage was only ever used as a store it never got wired up.
More recently as some other work was being done I put a much larger 16mm 3 core SWA feed over to the garage (only 1.2m from the house; total about 15m cable length to where the garage CU is planned) in anticipation of purchase of an EV (32A charge).
I assume even with the garage this close is is best to TT it, not export the earth.
Did wonder though whether to use the 4mm for the CU in the garage and just have the EV charge point direct, probably off a small CU added in the houseas the current board is already full (and yes the tails going to need upgrading fro m16mm to 25mm for those of you with sharp eyes)
Thoughts appreciated please.