I was doing a board swap today at a property with a tns supply with paper sheathed lead armored feeding it, I looked at the job previously and noticed there was no main earth from the lead sheath, there was an old style bonding cable connected in the board which I presumed went to the water which was being used as an earth. Iv contacted western and there coming out to swap to tncs in a couple of weeks. I have bonded water and gas with 10mm and left a 16 down to the distributor cutout so as of now theres no main earth, Is this ok as a temp until its swaped as the water bond was the main earth previously? ze, zs readings are ok, Cheers Matt :bucktooth: