J
James sparks
Hi all
Am looking for opinions on this one, I'll try and keep it brief.
Service cable comes in into a 3phase head (1361 100A). From the 3phase head to a Ryefield board. Single phase supplies (1361 60A) out of the Ryefield into single phase meters. SWA sub-mains from meters to flats.
Would you say the origin is TPN or SPN? The meters only offer a single phase supplies and the Ryefield etc is before the meter (so their property) but, it does enter/originate at a TPN service head.
Existing EIC has 60A 1-phase 2 wire as supply characteristics.
Is it a TPN supply/origin or becuase all of that is before the meter it's only a SPN that concerns us as the origin? There's no 3phase meter so there's no readily available TPN supply to use.
Thanks!
Am looking for opinions on this one, I'll try and keep it brief.
Service cable comes in into a 3phase head (1361 100A). From the 3phase head to a Ryefield board. Single phase supplies (1361 60A) out of the Ryefield into single phase meters. SWA sub-mains from meters to flats.
Would you say the origin is TPN or SPN? The meters only offer a single phase supplies and the Ryefield etc is before the meter (so their property) but, it does enter/originate at a TPN service head.
Existing EIC has 60A 1-phase 2 wire as supply characteristics.
Is it a TPN supply/origin or becuase all of that is before the meter it's only a SPN that concerns us as the origin? There's no 3phase meter so there's no readily available TPN supply to use.
Thanks!