Afternoon chaps,
Just looked at a job
customer owns/works in a small office/shop- also owns the flat above- currently 1 flat over 1st and 2nd floors.
He is turning the flat into 1 studio flat and another flat. so total renovation and me to rewire.
current metering arrangement as follows:
shop has own single phase 80/100a head with own meter and c/u- inside shop
then flat has own single phase 80/100a head with own meter and c/u- inside flat on ground floor bottom of stairs.
No gas at the property so will be all electric.
Shop is very basic- has a 32a ring- probably <10 d.sockets, 1x 6a lighting circuit- around 20x led downlights, and a 16a under sink water heater (unsure of kw of heater)
In studio flat A- will be:
2x 2kw panel heaters
1x shower (he has bought a 10.5kw- but he now knows he will likely have to change that for a power show)
1x elec cooker
1x elec hob
around 10x led downlights
around 10x sockets
In flat B- will be:
3x 2kw panel heaters
1x shower (he has bought a 10.5kw- but he now knows he will likely have to change that for a power show)
1x elec cooker
1x elec hob
around 20x led downlights
around 15x sockets
even with him returning the 2x 10.5kw showers and using power showers- I still think having the 2 flats on the 1x 80/100a head is tad risky- but he doesn't want to pay for new supply or turning the single phase head into 3ph.
Would splitting the 80/100a head in the shop by henleys- getting supplier to put a 2nd meter in (ideally local in the studio flat rather than in shop) and run a 16/25mm 3core swa from shop head directly above through ceiling into studio flat above (this area will be kitchen- so have the c/u and meter in some kind of boxing the - run <5m so would have to put in a sw fused isolator.
thoughts please
Just looked at a job
customer owns/works in a small office/shop- also owns the flat above- currently 1 flat over 1st and 2nd floors.
He is turning the flat into 1 studio flat and another flat. so total renovation and me to rewire.
current metering arrangement as follows:
shop has own single phase 80/100a head with own meter and c/u- inside shop
then flat has own single phase 80/100a head with own meter and c/u- inside flat on ground floor bottom of stairs.
No gas at the property so will be all electric.
Shop is very basic- has a 32a ring- probably <10 d.sockets, 1x 6a lighting circuit- around 20x led downlights, and a 16a under sink water heater (unsure of kw of heater)
In studio flat A- will be:
2x 2kw panel heaters
1x shower (he has bought a 10.5kw- but he now knows he will likely have to change that for a power show)
1x elec cooker
1x elec hob
around 10x led downlights
around 10x sockets
In flat B- will be:
3x 2kw panel heaters
1x shower (he has bought a 10.5kw- but he now knows he will likely have to change that for a power show)
1x elec cooker
1x elec hob
around 20x led downlights
around 15x sockets
even with him returning the 2x 10.5kw showers and using power showers- I still think having the 2 flats on the 1x 80/100a head is tad risky- but he doesn't want to pay for new supply or turning the single phase head into 3ph.
Would splitting the 80/100a head in the shop by henleys- getting supplier to put a 2nd meter in (ideally local in the studio flat rather than in shop) and run a 16/25mm 3core swa from shop head directly above through ceiling into studio flat above (this area will be kitchen- so have the c/u and meter in some kind of boxing the - run <5m so would have to put in a sw fused isolator.
thoughts please