H
hduz5
Hi Guys,
Looking for a bit of advice re volt drop and PV installations as I'm getting confused.
For example, a domestic job where the property has an outbuilding with a south facing roof. The customer already has a 100m length of 6 mm cable feeding the outbuilding. They wish to install a 3.96kw system on the outbuilding, but don't want to pay to have a new supply cable installed. For FIT purposes they want the inverter and the generation meter installed in the outbuilding so they get paid for all the electricity they generate. Does locating the meter and inverter there contravene any regulations?
Secondly, the set up gets run through sma design software and it hypothetically says that this system will have losses of 5% on the cable (don't know the actual figures, just making these up for an example). Is this a problem, other than 5% of the electricity being produced being wasted? If you were to take this to the extreme, could the system operate with 99% losses on a cable run, and still successfully import the 1% into the grid? What are the consequences of this? Is it dangerous or just massively wasteful?
Apologies if this isn't the clearest post. If anybody can shed any light on any of these issues I'd be very grateful.
Cheers
Looking for a bit of advice re volt drop and PV installations as I'm getting confused.
For example, a domestic job where the property has an outbuilding with a south facing roof. The customer already has a 100m length of 6 mm cable feeding the outbuilding. They wish to install a 3.96kw system on the outbuilding, but don't want to pay to have a new supply cable installed. For FIT purposes they want the inverter and the generation meter installed in the outbuilding so they get paid for all the electricity they generate. Does locating the meter and inverter there contravene any regulations?
Secondly, the set up gets run through sma design software and it hypothetically says that this system will have losses of 5% on the cable (don't know the actual figures, just making these up for an example). Is this a problem, other than 5% of the electricity being produced being wasted? If you were to take this to the extreme, could the system operate with 99% losses on a cable run, and still successfully import the 1% into the grid? What are the consequences of this? Is it dangerous or just massively wasteful?
Apologies if this isn't the clearest post. If anybody can shed any light on any of these issues I'd be very grateful.
Cheers