W
woko
Hi, I was applying for >3.66Kw systems with weston power and getting a reply within a week.
I was told today they can promise a reply within 25 days!!! the jobs booked in for next week.
My LABC have also got involved with jobs now and I'm having to get a structual engineer report for them. I don't mind this beacuse I think the roof structure should be looked at first.
These two things are starting to slow things down, I'm unable to give people start dates until These things are satisfied. I'm also concerened that other local installers are not getting these things done.
Anybody else having similar problems?
I was told today they can promise a reply within 25 days!!! the jobs booked in for next week.
My LABC have also got involved with jobs now and I'm having to get a structual engineer report for them. I don't mind this beacuse I think the roof structure should be looked at first.
These two things are starting to slow things down, I'm unable to give people start dates until These things are satisfied. I'm also concerened that other local installers are not getting these things done.
Anybody else having similar problems?