Doing a kitchen refurb, adding new RFC etc. After stripping out all the old stuff, I'm left with a JB which will be inaccessible, which had been used to feed a spur form the existing house RFC. The spur leg has been removed, but still leaves the JB. Whoever did the JB, didn't cut the conductors, just removed the sheathing & insulation to do the joint.
Once the ceiling goes back up, this JB will be inaccessible. To replace this JB with an MF JB, will require some rewiring & damage to decoration to the room above, as the cables to JB will be too short.
What would you do, replace or leave as is?
Once the ceiling goes back up, this JB will be inaccessible. To replace this JB with an MF JB, will require some rewiring & damage to decoration to the room above, as the cables to JB will be too short.
What would you do, replace or leave as is?