Discuss Whats the process with running a new electricity supply from i.e EDF to fuseboard? in the Australia area at ElectriciansForums.net
Just wondering what the whole procedure is? What are the rules and regs associated with this etc? Whats the situation if your having a single phase or three phase board?
Thanks in advance.
John
Re: Whats the process with running a new electricity supply from i.e EDF to fuseboard
1: Apply to DNO for supply ( application for supply will be sent to you , you will proberbly need help to
fill in the form )
2: Appoint an electrical contractor to carry out new installation.( He will fill in
the form and ask you to sign it and return to DNO)
3: Contractor will then liase with DNO regarding connection, complition and certification of the new
installation)
4: Contractor will arrange connection
5: You pay contractor ( if you have not already done so)
Simples
Reply to Whats the process with running a new electricity supply from i.e EDF to fuseboard? in the Australia area at ElectriciansForums.net
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
Good to know thanks, one can never have enough places to source parts from!
OFFICIAL SPONSORS
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Thanks all for your comments, advice and suggestions. The following is probably pretty boring for most, and is simply a summary of how the job...