Okay, I know you have to use TT on a temporary building supply but cannot understand why? If the supplier is able to supply a TNCS why is this not preferable to a TT?
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Discuss Why TT on Temp Building Supply? in the Electrical Course Trainees Only area at ElectriciansForums.net
Section 704. 704.411.3.1
A PME earthing facility shall not be used for the means of earthing for an installation falling within the scope of this section unless all extraneous-conductive parts are reliably connected to the main earthing terminal in accordance with Regulation 411.3.1.2.
NOTE If the PME earthing facility is considered for use, see also BS7375.