kduck
Hi,
got to wire some storage heaters never done them before, is it therefore the customer would need a economy 7 meter fitted by electrical company, then from there in to a new c/u and each heater supply by a radial circuit wired in 2.5 and a 16amp mcb and a fused spur at each heater.
thanks
got to wire some storage heaters never done them before, is it therefore the customer would need a economy 7 meter fitted by electrical company, then from there in to a new c/u and each heater supply by a radial circuit wired in 2.5 and a 16amp mcb and a fused spur at each heater.
thanks