So a friend of mine has a new build (2020) typical new build lashed in. Hes getting an electric car soon however fitting a charger will be a pain in the backside as the meter cupboard is in passage on the side of the house the fuse board is fed by a sub main and is in the toilet under the stairs which is right in the middle of the house and its a semi detached. Top floor is all fitted flooring so no access that way. Behind the fuseboard is a fully fitted kitchen.

Only way it can be done is in the meter cupboard as the passageway is so tight that you'd never get the bins or anything through it if you fit an enclosure on the wall

My plan would be the fit a 7-8 module board in the meter cupboard and getting rid of the KMF switch feeding the house fuseboard

have the tails in to a 100A isolator then an SPD /SPDMCB if needed then dp rcbo for the car charger circuit then a 63a dp mcb for the house this at the end so that the neutral is on the lhs so no need to cut the busbar

Only problem is finding the parts all from the same manufacturer anybody had any experience of this?
[ElectriciansForums.net] Help with finding MCB
 
If you send a photo of the meter cabinet that would help

my own thoughts would be fit a 4 pole isolator and link it out so that it acts in lieu of a henley block etc from this run tails or other cable above meter cabinet and at a height out of the way of bins fit an enclosure to supply charger. this gives you your isolation and keeps the existing switched fuse. have you considered replacing the existing fuse/switch for a small one?
That said you can get 4 module rcbo/spd kits in an enclosure that are small enough you can fit in the meter cabinet alongside other things like henley blocks etc...
Make life easy for yourself and use 10mm tails for the ev charger before going in enclosures/rcbo etc you will be amazed what you can fit in a cabinet when you plan it well.. comes from installing 100s of chargers.
 
If you send a photo of the meter cabinet that would help

my own thoughts would be fit a 4 pole isolator and link it out so that it acts in lieu of a henley block etc from this run tails or other cable above meter cabinet and at a height out of the way of bins fit an enclosure to supply charger. this gives you your isolation and keeps the existing switched fuse. have you considered replacing the existing fuse/switch for a small one?
That said you can get 4 module rcbo/spd kits in an enclosure that are small enough you can fit in the meter cabinet alongside other things like henley blocks etc...
Make life easy for yourself and use 10mm tails for the ev charger before going in enclosures/rcbo etc you will be amazed what you can fit in a cabinet when you plan it well.. comes from installing 100s of chargers.
I forgot to take a picture annoyingly

but its essentiality this however the meter is a smart one that takes up the whole lhs ad then the KMF switch is at the bottom ish but as a skirt for the single insulation of the te

[ElectriciansForums.net] Help with finding MCB
[ElectriciansForums.net] Help with finding MCB
 
I would feel confident in moving things about and be able to fit a db henely block, the switched fuse and get a 4 mod minin consmer unit in there with rcbo/spd.
Often do it. wont ask how you are isolating supply - (of course call dno to isolate!) but flexi tails would be very helpful here
 
Yeah neither would I but sometimes these things happen







I'll have another look next time i'm over and have a rethink







New build houses seem to be built with no foresight for alterations







Fuseboard is a mess as well. no SPD, dual rcd, some labels written by sharpie, mis match of plastic blanks







fitted by a mas.sive company too saying no names
 
Last edited by a moderator:
That's a very dismissive approach to something which is going to reduce the installation's compliance with the regulations.

Whats preventing you from using a fuse to protect the submain in your new setup?
Room, as the cable comes side entry so will be hard to jig everything around with the length of cable unless i slacken the meter box from the wall and try bring the cable down from above but i'm sure i read somewhere you can't bring cables from above in meter boxes
 
Room, as the cable comes side entry so will be hard to jig everything around with the length of cable unless i slacken the meter box from the wall and try bring the cable down from above but i'm sure i read somewhere you can't bring cables from above in meter boxes

If you have space for an MCB you have space for a fuse.

Where did you read that? It's not a regulation I've heard of before.
 
If you have space for an MCB you have space for a fuse.

Where did you read that? It's not a regulation I've heard of before.
Well it would be fine to do now I guess as its already installed so nobody would know

I can't actually find it written down lol so maybe he made it up but when I was a an apprentice back in 2015 we changed some houses to flats with their own supplies and matey from UKPN wouldn't approve the connection because we had run the cables from the top of the meter box and he wanted them entering from the bottom.
 
Well it would be fine to do now I guess as its already installed so nobody would know

I can't actually find it written down lol so maybe he made it up but when I was a an apprentice back in 2015 we changed some houses to flats with their own supplies and matey from UKPN wouldn't approve the connection because we had run the cables from the top of the meter box and he wanted them entering from the bottom.

"it's already installed so nobody would know" doesn't feature in the regulations.

"matey from UKPN says" isn't a regulation either.
 

Reply to Help with finding MCB in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

  • Question
Why not fit a self contained SPD fed directly from the Henley blocks, and free up a bay? Could probably make one up from whats there, using a...
2
Replies
47
Views
4K
  • Question
What is the distance from the point outside the house to the shed?
Replies
8
Views
641
Found the cause of the tripping…. Just jointed them through… all clear now. Removed the smoke detectors completely. They were due to be...
Replies
6
Views
668
When he bought the bank, they stripped out all the metalwork, iron bars etc for scrap. He was left with the cashier countertops… which have been...
Replies
2
Views
322
  • Question
If it's buried ducting, have you thought about digging up a section of the buried cable close by, cutting it and pulling in a few extra meters...
Replies
6
Views
642

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock    No Thanks