I've just been sent this, not been there yet. At least 2 new circuits needed and things are a little.....tight...!
Hager board is 10 modules and full. RCD main switch.
They reckon they have an earth rod outside, deciphering connections to left of the head will need better photo. So earthing details TBC.
I'm trying to decide if I even try to change that board - yet another Hager with main switch RCD, as I could add a new CU elsewhere.
But main question - am I thinking straight regarding this (unsealed) meter - and that it looks like it might be redundant?
If it were it opens up some options for a bigger CU.
Hager board is 10 modules and full. RCD main switch.
They reckon they have an earth rod outside, deciphering connections to left of the head will need better photo. So earthing details TBC.
I'm trying to decide if I even try to change that board - yet another Hager with main switch RCD, as I could add a new CU elsewhere.
But main question - am I thinking straight regarding this (unsealed) meter - and that it looks like it might be redundant?
If it were it opens up some options for a bigger CU.