Best practice for moving a consumer unit. | on ElectriciansForums

Discuss Best practice for moving a consumer unit. in the UK Electrical Forum area at ElectriciansForums.net

T

Thomps

Just been to see a job and the guy wants his consumer unit moved. It is curently in his kitchen and he changing that to a bathroom and building a new kitchen in the extension. The original wiring looks to a decent standard so i will be looking at extending the wiring from some sort of din rail terminal system to the new board.

Do you have to use spring terminals or is it ok to use a screw terminal? Is it acceptable to join the 10mm bonding or is it a no no?

This is the first time i've ever moved a board so any advice would be appreciated.
 
[ElectriciansForums.net] Best practice for moving a consumer unit.like these
 
If the original location is going to be a bathroom, then remember to use a box suitable for that location. There are plenty of IP55+ enclosures on the market, although I'm sure the client will want it boxed in somehow. Just make sure there is access to the box, unless you are installing either the LineProducts MF kit or the Ashley MF kit, as simply using push-fit connectors will not make it MF.
Of course, you could always crimp and sleeve inside the box if you have a suitable ratchet tool.
 
Thanks all.

Am i right in thinking that it would be ok to use insulinks covered in heat-shrink which is contained in a suitable enclosure? And is this a recognised MF method or would it have to be accessible?
 
The meter is also getting moved, but not by me, to the same location as the new CU.

funnily enough me an Telextric had a conversation about this the other day and to me an adaptable box and din rails all the way it was the same scenario to moving the CDU from a room to what was going to be a bathroom heres the pic of the extension box[ElectriciansForums.net] Best practice for moving a consumer unit. the connectors are wago push in din rail mounts so easy to use to0
 
that's a lovely neat job, nick. my install this week is a lot less circiuts than that. i'm just debating with myself whether to go for LNE.LNE, etc. or LLL NNN EEE, etc.
 
that's a lovely neat job, nick. my install this week is a lot less circiuts than that. i'm just debating with myself whether to go for LNE.LNE, etc. or LLL NNN EEE, etc.

thank you Tel thats the one we were talking about the other day mate , each circuit was as it is so you have a ring its LEN LEN . then the next circuit LEN , its the way ive always done it just stuck
 
Last edited by a moderator:
Personally, when moving a CU I use crimps and SA tape, that way the cables can be buried in the wall (providing they're in a safe zone). Then again, it all depends on where the existing CU is and where it's moving too. If all the cables are surface mounted then I'll use a DIN rail box.

I had a job a while back where I had to change and move a CU due to moisture problems causing a fire within the existing CU. The cables were all behind stud wall so when moving the CU, I used crimps and SA tape to allow them to be run behind and along the wall then I used a nice piece of 3mm sheet metal to protect the cables that ran through 'non' safe zones.
 
Why not do away with all the connections altogether. For example, for a ring main in the old CU traced back to the first two sockets and connect them up to each other, then break into that circuit from the new CU. A lighting circuit feed would be removed from the old CU and a new feed put in from the new CU. I understand it may be more work, or would it if the new extension causes floorboards to be lifted. Certainly removes unnecessary conections/jointboxes in a bathroom?
 

Reply to Best practice for moving a consumer unit. in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

  • Question
What is the distance from the point outside the house to the shed?
Replies
8
Views
635
M
  • Question
I meant EIC, No idea why I put EICR down, thanks for the clarification
Replies
13
Views
1K
  • Question
seems to be a big song and dance over this one guys, this is bottom basement stuff and seriously I cannot believe one the thread was put up and...
Replies
10
Views
1K
Yes the first bit is just standard wiring, TNS lead cable into cut-out, cut-out to meter, meter to DP isolator, top of isolator is sealed as per...
Replies
8
Views
945
  • Question
Rough is being exceedingly generous. Never ceases to amaze me what people will walk away from. That could have been so much better with a little...
2
Replies
30
Views
6K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock    No Thanks