  1. S

    G83 - New install in same street

    My understanding is that you do not have to pre notify because of the 28day rule. There used to be a sticky on here with a link to the document on the thread buts its been moved. don't have the documents to hand to send the link. call the DNO to point you in the direction of document.
  2. S

    First 50kW ground mount - help

    Any idea how much time to allow for the installation - for those of you that have done smaller installations, how much longer did it take than a trapezoidal roof?
  3. S

    First 50kW ground mount - help

    M&D Doncaster can't help. I've put in a call to Renusol though who seemed very helpful - as are you guys!
  4. S

    First 50kW ground mount - help

    Where abouts are they based Spitfire?
  5. S

    First 50kW ground mount - help

    Can't use consoles as the client is concerned with flooding, so wants a frame with 1m clearance from the ground to the lowest part of the panel. all cables will be contained above 1m, and there is very little risk that water will rise above 1m.
  6. S

    First 50kW ground mount - help

    Just looking at 50kW (200 panels) ground mount system. Got all the quotes in for the kit (Shuco and Schletter), got provision for planning permission & DNO application is covered (including relay if required). Any advice on whether I need to have a ground survey carried out and if so, can you...
  7. S

    Green deal in the press.

    Just interested to see whether those that have registered as advisers/assessors are fully geared up for GD? I remember a while back someone said that they still had not seen the software to input the assessments yet - has this been resolved yet?
  8. S

    SSEG Application for connection of multiple G83/2 installations

    Has anyone had to apply for the G83/2 yet for multiple installations? Just wondering if any have been refused, though it did come into force in one of the quietest times of the year,!
  9. S

    Console Job

    nice install! We have used these quite a bit (sorry, didn't see your original post to comment). Only used them on a flat roof and found them very good, especially when you can't place in a block formation because of obstacles on the roof; however, we have found that the ballast recommended by...
  10. S

    Funder required

    Are there any funders out there at the mo? Have a client wanting 50kW on south facing roof, plus there is space for another 50kW on a SE roof in Huddersfield area. They have high usage on site and are willing to enter into a reduced electricity cost agreement.
  11. S

    Large solar array 40KW 160 panels, welcomed thoughts!!

    I didn't know that!! I'm gonna check with my planning officer about permission I submitted before christmas to see about the Article 4 as I was told that I would need permission, but they were a bit vague on a couple of other points surrounding permitted development.
  12. S

    Large solar array 40KW 160 panels, welcomed thoughts!!

    agree with the comments above. You should still check with the local planning officer that the area is not in a conservation area. If it is then permitted development is overruled and you need to apply for full planning. If it is then check with them what type of drawings and illustrations...
  13. S

    Planning permission when not permitted development

    They are commercial jobs, thermal mounted on a flat roof with A frames. We have done commercial before on roofs before permitted development rules changed and were charged £195. In this case, 2 diff buildings, 2 diff councils, 2 diff prices. The only difference is that 1 building is flat roof...
  14. S

    Planning permission when not permitted development

    What are you guys getting charged for planning permission when pv/thermal doesn't come under permitted development? I have been charge £195 by one council but another council wants £385 as they view it as plant/machinery.
  15. S

    single phase upgrage/FIT

    talking to a customer who has 2.94 installed and he wants to increase this to over 4kw (subject to DNO). My question is: If his incoming meter is change to a 3 phase with a new MPAN, will he loose the FIT rate on the existing 2.94kW?
  16. S

    New Cost Effective Installation Method?

    nice - am running it past my guys now....NOT!
  17. S

    Steca TKRW2 - solar thermal monitor

    Thanks Puddy, we have distances to consider and I am trying to get confirmation from steca that it will work with the specifications of the tablet we are looking at. There is no app unfortunately. Anyone used the steca monitor specifically?
  18. S

    Steca TKRW2 - solar thermal monitor

    I am at a loss with the support from steca at the mo for a thermal job we are installing the monitoring on. The TK RW2 has been recommended as we need both online visability of the performance and also a display in the client's reception area. Has any one used this kit? if so, can you advise...
  19. S

    Will finance packages help?

    If you offered a finance package to a customer as well as a price to buy outright then it gives the customer the option. some customers wont even think about it because the interest rates add on to the payback by about a year or more.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top