This is for the young punks who think they know a bit about real switchgear, and the old geezers who might just remember seeing the results one of these things produces. I've just got this running, probably last used in the 1970s, the building it was in was knocked down in '82.
If no-one...
Hi all, (not the standard domestic setup for me)
-3 phase overhead supply TT. coming in via 3 200amp fuses (not sure what type so unsure what to write on cert) any ideas?
-Then goes to large rusty switchfuse (see pic). Bs3185?? Earthing conductor straight into concrete.
-Fairly large swa...
I have an assignment for my 2365.
Question asks to list 3 methods of connection that may be used during the installation of an apartment block and a workshop.
I have screw clamping terminals for accessories.
I have screw-less terminals as an alternative.
What else?
Would compression...
Hi guys,
As I post in the head of the topic I am loking for some theory about the above things.I was looked here in this chapter but I can not find nothing.So if somebody of you have some materials about that I will be very thankful to send it to me.Or paste some links here.I prefer somthing for...
Hi guys after a recommendation for some switchgear iv got a 70mm 4core Swa going in which I'm doubling the cores up as a single phase supply due to voltage drop. Eddys have quoted me on a wylex nhspsf100 which is only good upto 50mm. Ideally I'd like bolt on terminals to lug the 2 parallel 70mms...
Afternoon all,
I am in the need of ten mechanical interlocks for MTE UCO 60-100 isolators, surfing the net up and down, no joy.
does anyone maybe know a supplier or distributor, please? Don't fancy the idea of replacing the isolators. Don't know why the interlocks went missing, probably fallen...
OK peeps
I have just tested an 185 4 core SWA, and have got readings of 40 Megs on L2 to earth and L3 to earth. Although this is accepatable according to the regs, I feel it is unacceptable as a NEW installation, and indeed there is evidence of water on some of the switchgear, which clearly...
Hi,
I run an electrical testing company mainly doing EICR for schools, hosptitals etc and am incresingly getting asked to do switchgear testing for the facilities.
Anybody help with level of training and standards required to do this? Any info on companies wich provide training would be a great...
Guys we have been asked to replace a very old switch fuse. It is 800A 400V approx 30-40 years old. We believe it is oil filled, likely to be containg PCB's. Is there a safe way to go about replacing this? Even opening the switch to inspect the internals may mean coming into contact with the oil...
Hi, I am new so I need to get some posts going. I am not a registered spark I am more of a technical contracts engineer. I am looking at if it possible to have a generator which backs up the mains supply (auto change over) but also is connected in parallel so can export to the grid. I am not...
Hi There
Looking for some advice about reliability of certain brands of switchgear. I am building a custom three phase distro on a value for money budget and was trying to use crabtree but they do not do certain things I need such as non specialised RCD's. I am looking for non chinese made kit...
I was reorganising our stores the other day and came across a number of old / discontinued single pole and triple pole circuit breakers. They include:
Federal Electric / Stablock
Dorman Smith
Wylex
Crabtree
MEM
On many occasions I've been asked to install new circuits in old industrial units...
I was assembling a large distribution unit today. Hager type with a 500A main switch. There are 10 x 100A MCCBs going to be installed The board, MCCBs etc came in a kit, which also had a surge protection device with it. The client did specify the nee for the SPD however the SPD itself has...
Hopefully this one will be a simple one to answer.
A lift in a premises as been determined as a fire lift (to be used in evacuation under fire conditions)
the lift as to have 2 supplies of power, with basically switchgear (not provided in the lift electrics) that would simoultaneously cange the...
Hey guys, I keep hearing these terms being thrown about, but am still unaware of the difference between the two? Can anyone enlighten me? And can I get a couple examples of each? I have searched but have no luck yet, cheers!
Can anyone please explain how can i select contactor,olr/mpcb,acb for a particular load for DOL? What should be the maximum load on the switchgear? Should it be 100% or less?
I don’t know if any of you have ever operated or have to operate DMO Dependant Manual Operation switchgear. I found this interesting reading
http://www.hse.gov.uk/foi/internalops/fod/oc/400-499/483_27.pdf
Most of this gear should have been replaced years ago, but there are still bits of it...
Three phase boards and switchgear used for 480V split phase. OK or not?
Hi from a newbie.
I have already bought all the DBs and equipment for a major rewire and extension at my old farmhouse in Norfolk. I was expecting to have the existing ‘split-phase’ 240/480V supply (from antique...
Hi All,
I've just been reading the IET wiring matters magazine and there is an article saying that mcb lock-out devices can be obtained FOC from switchgear suppliers.
As I am just starting up as a spark then I haven't got any of these. Do I just need to contact Wylex and the like for them ...
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc