Afternoon all..
A couple of questions..
I shall be installing an 80A switch fuse after the cut out as both the supply and the CU are being moved and they will be greater than 3m apart. There will be approx 2m of tails on the outside wall in conduit and the remainder (approx 8m) will be between the floorboards (without insulation)
1. I am planning to use 25mm tails simply because this is recommended by the on-site guide and for rewires this again seems to be the recommendation, or rather the 'good practise'. My question is why would 16mm tails not be acceptable? If reference method C is used then 16mm has a CCC of 87A, also I believe the voltage drop is ok given a max demand of 80A (haven't got the tables to hand).
2. I can see where the incoming supply cable enters the house so I want to install and position the new meter box myself so that the DNO will have to 'shorten' their supply cable rather than joint it. The reason I want to do this is because I want to get my switch fuse in the new meter box before they fill it up, as they may not position the meter and cutout with my switch fuse in mind, whereas I will consider their needs.
Is it ok for me to install the meter box and pop my switch fuse in before they do there bit?
Cheers.
A couple of questions..
I shall be installing an 80A switch fuse after the cut out as both the supply and the CU are being moved and they will be greater than 3m apart. There will be approx 2m of tails on the outside wall in conduit and the remainder (approx 8m) will be between the floorboards (without insulation)
1. I am planning to use 25mm tails simply because this is recommended by the on-site guide and for rewires this again seems to be the recommendation, or rather the 'good practise'. My question is why would 16mm tails not be acceptable? If reference method C is used then 16mm has a CCC of 87A, also I believe the voltage drop is ok given a max demand of 80A (haven't got the tables to hand).
2. I can see where the incoming supply cable enters the house so I want to install and position the new meter box myself so that the DNO will have to 'shorten' their supply cable rather than joint it. The reason I want to do this is because I want to get my switch fuse in the new meter box before they fill it up, as they may not position the meter and cutout with my switch fuse in mind, whereas I will consider their needs.
Is it ok for me to install the meter box and pop my switch fuse in before they do there bit?
Cheers.
Last edited: