As I promised I would try and post things on here in the hope it might help some of the lads that perhaps don't do larger jobs
Below is another of my builds here. This one is different from the first in that it is a metal framed prefab made of external sandwich panels The left is the steel work going up, the right is this morning 2 weeks later!
Because it is steel framed I have slighlty different earthing issues as I need to bond the frame. The left hand picture is the Bond for the building.
I sized originally a 50mm but we literally had 70mm on the "van" so I used that. The middle picture is entry back into the building from my earth pits, Eventually it will be a manhole and the lightning/functional earth/bonding will all come back into the building and then onto the MET.
The right hand picture is one side of the building that is being compacted and where I will put 3 pits and rods.
These final 2 pictures are going to be too large ops rooms. Originally I designed a floating floor and using power trunking, because I wanted the flexibility of moving desks etc around. Unfortunately out here there is a 16-18 week lead time for power trunking, and the occupancy is scheduled for January. So we have had to go back to floor boxes for power/data and we are using DADO trunking for the wall mounts
I'll try and take more pictures as the build progresses
Below is another of my builds here. This one is different from the first in that it is a metal framed prefab made of external sandwich panels The left is the steel work going up, the right is this morning 2 weeks later!
Because it is steel framed I have slighlty different earthing issues as I need to bond the frame. The left hand picture is the Bond for the building.
I sized originally a 50mm but we literally had 70mm on the "van" so I used that. The middle picture is entry back into the building from my earth pits, Eventually it will be a manhole and the lightning/functional earth/bonding will all come back into the building and then onto the MET.
The right hand picture is one side of the building that is being compacted and where I will put 3 pits and rods.
These final 2 pictures are going to be too large ops rooms. Originally I designed a floating floor and using power trunking, because I wanted the flexibility of moving desks etc around. Unfortunately out here there is a 16-18 week lead time for power trunking, and the occupancy is scheduled for January. So we have had to go back to floor boxes for power/data and we are using DADO trunking for the wall mounts
I'll try and take more pictures as the build progresses