guitarman
wonder if anyone can help. ive just purchased a 9bedroom house, and have approved planning for 5 flats, the house was commercial before (a womans refuge) there is a 3 phase board there but unfortunatley only a single phase supply. as i am going to require 4 new supplies in total, im wondering if its cheaper to request 2 x 3 phase supplies, my reckoning is it might be cheaper and hopefully i will only have to dig 1 trench. can anyone advise me on these possibilities or point me in the right direction? thanks in advance.