working days?

northern powergrid / YEDL are now taking up to 65 working days for G59 btw, 45 for G83 stage 2
 
no not working days just spoke to them 30th august is his limit sent it beginning of july

- - - Updated - - -

How can 65 days work within the tariff time scale
 
I dont know, need advice from someone about this, sent of 3 at same time the other two have been passed and finished.
I have another to send to the same guy and the will take into Nov
 
The DNO I spoke to had the pleasure in saying we have 45 days to get back to you so expect the 45 days to be used from us, not our problem about the FIT sorry. (jobs worth)
 
The evidence becomes more overwhelming every day. The energy companies don't want people producing their own electricity.
 

Reply to the thread, titled "4x4kw multi installation" which is posted in the under the Solar PV Forum | Solar Panels Forum on Electricians Forums.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
Back
Top