Hi all,
According to my calculations (CCT9) - I am getting a 50A breaker on the sockets in the changing rooms leaving me with a 10mm cable to install. The reason why is because I’m calculating the sockets at full load.
Cable length 13.4m
Design current of 40.70A
Ambient temperature of 40c
Ref method B
90 degree PVC conduit
Is this viable or do I need to rethink my design?