Evening,
Im working for a builder on a kitchen extension..
Now the usual procedure with this building contractor is do the essential checks (bonding, Ze ect) make sure its up to scratch and fit a separate board to feed my new circuits... nice and simple
However im just finishing the first fix and it turns out the client expects the house board to also be updated (rewireable fuses and no RCD protection). The builders spec doesn’t specifically ask for this so its not been included by him but hey ho its an extra for me at the end of the day.
The place is a big house and while doing a walking round it is evident that there is ongoing work by other contractors in the bedrooms and additional en suits/wetrooms. Which started last year prior to me and is still not finished.
There has been a shed load of electrical work carried out in these new suits (underfloor heating, towel rails, downlights, cabinet lighting, PIR switching/dimmers and wall lighting).
As I mentioned no RCD protection is installed so no wonder the client is fairly adamant the board change is included in my builders spec.
I asked for any certification issued to the client for works carried out but its not been done.
The work seems ok from what I can see...
Then I found metal cased double insulated wall lights in the bathrooms that have not been installed correctly with the t and e stripped and brw/blu conductors ran into the fitting (no grommet) and connected with wagos. One knock of the fittings and the case could become live with pipe work and towel rails in reaching distance.
Pulled it up as being dangerous with the client and asked why the installation was started without at the very least an RCD fitted in the first place. They said that the previous electrician who did the work was aware of the requirement for RCD protection but was told by the client that the board was being upgraded so don’t worry.
... would you put yourself in this position?
I wouldn’t
Way I see it I have a few options
1. Remove the dangerous fittings, isolate the feeds at the dimmer and risk the client reinstalling them back himself. Reinstalling them properly will be difficult as the plastic joint box and rubber cable sleave has been thrown and with the fitting being mounted on espensive tiles, hes not going to want to leave a hole where they was fitted.
Then test the lot and then do the board change.
2. Be persistent and ask for the previous electrician to rectify the lights, test the work and issue a certificate taking responsibility for the works.
3. Knock the board change on the head all together and tell the client to get the electrician back to do it and certify his work.
I have never certificated other peoples work and I really don't want to start now.
Any advice?
Cheers
Im working for a builder on a kitchen extension..
Now the usual procedure with this building contractor is do the essential checks (bonding, Ze ect) make sure its up to scratch and fit a separate board to feed my new circuits... nice and simple
However im just finishing the first fix and it turns out the client expects the house board to also be updated (rewireable fuses and no RCD protection). The builders spec doesn’t specifically ask for this so its not been included by him but hey ho its an extra for me at the end of the day.
The place is a big house and while doing a walking round it is evident that there is ongoing work by other contractors in the bedrooms and additional en suits/wetrooms. Which started last year prior to me and is still not finished.
There has been a shed load of electrical work carried out in these new suits (underfloor heating, towel rails, downlights, cabinet lighting, PIR switching/dimmers and wall lighting).
As I mentioned no RCD protection is installed so no wonder the client is fairly adamant the board change is included in my builders spec.
I asked for any certification issued to the client for works carried out but its not been done.
The work seems ok from what I can see...
Then I found metal cased double insulated wall lights in the bathrooms that have not been installed correctly with the t and e stripped and brw/blu conductors ran into the fitting (no grommet) and connected with wagos. One knock of the fittings and the case could become live with pipe work and towel rails in reaching distance.
Pulled it up as being dangerous with the client and asked why the installation was started without at the very least an RCD fitted in the first place. They said that the previous electrician who did the work was aware of the requirement for RCD protection but was told by the client that the board was being upgraded so don’t worry.
... would you put yourself in this position?
I wouldn’t
Way I see it I have a few options
1. Remove the dangerous fittings, isolate the feeds at the dimmer and risk the client reinstalling them back himself. Reinstalling them properly will be difficult as the plastic joint box and rubber cable sleave has been thrown and with the fitting being mounted on espensive tiles, hes not going to want to leave a hole where they was fitted.
Then test the lot and then do the board change.
2. Be persistent and ask for the previous electrician to rectify the lights, test the work and issue a certificate taking responsibility for the works.
3. Knock the board change on the head all together and tell the client to get the electrician back to do it and certify his work.
I have never certificated other peoples work and I really don't want to start now.
Any advice?
Cheers