Hey all, Well ive just booked my AM2 but i have to say i'm pretty nervous about now lol.

Has anyone recently done it, how did you find it?

I think my main concern is the solar element in the heating plan, as not sure what to expect there and probably the fault finding as ive not done much fault finding for a little while.

Any tips/hints much appreciated
 
Guessing no one has recently done the AM2??

I've noticed on other am2 threads the lighting circuit has been discussed and talk about feeding the neutral through the switches. As the task is asking for PVC PVC the only way I can see you can achieve that is by using 2 x T&E as you'll need 4 cores, is that really an acceptable way or am.i over thinking it?
 
For the AM2 you would wire as the plan states.
However there are two general methods of wiring lighting: two wire or three wire.
Either of these can be switch fed or triplate wiring as well.
The choice would be down to the installer and the layout of the switches and the lights and the wiring run between them.

If you were wiring in the two wire method when you feed the neutral through the switches you would only need a three core cable between the switches.
 
Thanks but I'm confused a little because of your doing two way and intermediate with the ceiling rose being fed you would use 3 core between the 2way and intermediate which would be your permanent live and the 2 strappers, it would be a core short if you were required to fed the switch with the neutrals to?
 
If you were feeding the switch and doing intermediate switching and wiring in flat PVC cable from the MCB to the switches and then to the light, it could be wired like this.
Two core from CU to 1st switch, three core between switches, two core from last switch to light.
(the red sleeving should be brown, it colour changed as I converted the image)
[ElectriciansForums.net] AM2 - anyone recently done it?
 
does this mean you get the neutral, but lose the permanent live though?
 
ahh im with you now, thanks for that diagram that helped a lot.
Your wiring the switches in reverse as such (when feeding the light) as you dont need the permanent live to go in and out of the first switch (coming back on the switched live) just in one end and out the other lol
 
@Karin
The permanent line only goes to the common terminal of the first switch, that line will swap back and forth between the strappers as you switch, the light fitting will only have a switched line.
 
Just in case it may help this diagram shows the four general ways in which you can do two way switching, there are a lot of modifications that can be done moving the position of the light and the supply in various ways but this is the general principle.
[ElectriciansForums.net] AM2 - anyone recently done it?
For the two wire three plate wiring this can usually only be done in singles in containment as it requires a single core to each switch (though in old wiring this is what was done: a single core red cable from light to switch occasionally with an earth, just wandering under the floor!)

To do three way or intermediate lighting you really just insert an intermediate switch wired in between the L1 and L2 of each 2 way switch as I have modified the above diagram to show below.
[ElectriciansForums.net] AM2 - anyone recently done it?
 
Afternoon, so i've just finished day 1 of my AM2 and could do with a little help, had a few hiccups today, but in the main i feel its going reasonably well

Basically i'm doing the practical now and have a few questions hopefully someone can help me with
1) DOL, i've wired to the DOL as per spec in singles but i cant for the life of me remember how to calculate the rating for the starter, its a 3 phase 0.37kw motor. Also coming out the DOL its being wired in SY, but there is no obvious earth point within the starter, there is a metal back plate and i did think to connect the incoming earth and the outgoing earth inside the SY using ring crimps to this, however that still leaves the SY unearthed, should i add an earth nut or banjo to the SY gland and just earth it all there and should iearth the sy sheath at both ends?

2) The FP circuit, all wired but in a quandary as the spec says to make sure you use the correct compartment within the compartmental trunking (all of them do), initially i placed it in the top compartment keeping it separate (alarm cable) but its not, as its being used as the feed for the spur so is mains, so have now moved it into the center compartment sound right.

I feel comfortable with the rest and i have 2.5 hours left to do the lighting circuit (thanks for the help earlier in the thread richard burns), finish the motor connection (just the SY part) and i have 2 more cables to wire into the heating system. Amazingly the heating system was my biggest fear and i have found that the simplest.
 
i missed the responses to this. just to confirm then, is there a reason for wiring the neutral to the switch (other than that it might be easiest)? i had thought it might be so one is available for future additions to the circuit but then of course at one switch you have a neutral but only a switched line
 
yes it could be easier if your going past the switch first makes sense, less cable used passing the switch to go to a light and back again, but in the case of the AM2 its what they have spec'd
 
Afternoon, so i've just finished day 1 of my AM2 and could do with a little help, had a few hiccups today, but in the main i feel its going reasonably well

Basically i'm doing the practical now and have a few questions hopefully someone can help me with
1) DOL, i've wired to the DOL as per spec in singles but i cant for the life of me remember how to calculate the rating for the starter, its a 3 phase 0.37kw motor. Also coming out the DOL its being wired in SY, but there is no obvious earth point within the starter, there is a metal back plate and i did think to connect the incoming earth and the outgoing earth inside the SY using ring crimps to this, however that still leaves the SY unearthed, should i add an earth nut or banjo to the SY gland and just earth it all there and should i earth the sy sheath at both ends?
If you are given the full load current set the overload to that current.
If you only have the 0.37kW rating at 400V then an approximation can be made using W/(1.732Ă—400*pf)
pf may not be required for the AM2.

Strange
there is no earth point in the starter.
The SY sheath should be earthed at at least one end of each cable.
There should be continuity across the starter for the earthing. and this should be a convenient place to earth the SY sheath.


2) The FP circuit, all wired but in a quandary as the spec says to make sure you use the correct compartment within the compartmental trunking (all of them do), initially i placed it in the top compartment keeping it separate (alarm cable) but its not, as its being used as the feed for the spur so is mains, so have now moved it into the center compartment sound right.
Fire alarm circuits should be segregated from non fire alarm circuits and FA ELV circuits should be segregated from FA LV circuits.
I would put it separately because the supply to the FA should not be disrupted because of actions on other circuits causing damage.


I feel comfortable with the rest and i have 2.5 hours left to do the lighting circuit (thanks for the help earlier in the thread richard burns no problem), finish the motor connection (just the SY part) and i have 2 more cables to wire into the heating system. Amazingly the heating system was my biggest fear and i have found that the simplest.
My ideas in red above, hopefully useful.
 
i missed the responses to this. just to confirm then, is there a reason for wiring the neutral to the switch (other than that it might be easiest)? i had thought it might be so one is available for future additions to the circuit but then of course at one switch you have a neutral but only a switched line
Obviously convenience is a factor, but it can also permit neons, remote switches, timers, sensors and such like to be powered at the switch. However it would not be possible to continuously power something on the two wire two way wiring end switch. This method is often called conduit wiring because it is simple to do in conduit.
 
Thanks Richard, FLC is what im going to look for to set the overload, there is a chart on the wall but too much info to take in and remember to bring here lol but im thinking as this is the AM2 the info has to be there rather than me calculating it

With the SY / Starter i may have missed the earth point so will look again, i was hoping there would be somewhere to earth the case because the sy gland would then be earthed through the casing

Im still unsure on the FP cable for the C02, its carrying 230v so is rated the same as the other cabling in the centre compartment but its also a service cable for the C02, i think my other reason for moving it to the middle is the fact it keeps the top compartment free for ELV cable which they could say i have messed up by using it, if that makes sense?
 

Reply to AM2 - anyone recently done it? in the Electrical Course Trainees Only area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
664
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
1K
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
2K

Similar threads

Hi Lou thanks for this. I am an NICEIC contractor and kindly been given a grace period to complete my experienced worker L3 NVQ. Sitting my AM2E...
    • Like
Replies
3
Views
807
From the front cover of the manual: Newlec Helpline: 0800 783 6909 https://www.manualslib.com/manual/3408290/Newlec-Nlsh050.html#manual I think...
Replies
1
Views
364

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top