Hi gents I registered on this forum to hear your thoughts on the following please
its a barn conversion / cottage alteration and full rewire. I've priced for the cottage part as she wants it done in stages since there's a lot to do on the barn section before it's ready for electrics. Anyway apparently I've been beat on my price and I'm baffled
as followed; the cottage has 3 large bedrooms with 2 ensuites and a main bathroom , hallway stairs etc.
11 x double sockets through out
15 x chrome down lights
10 x tilt chrome down lights
7 x ip rated chrome down lights
5 x centre lights ( pendants)
each room has a 2/3 gang switch to switch lights separately
2 x mains smoke detectors
3 x timer fan installation 4 inch with isolation switches. Core holes excluded
3 x 9.5 kW shower supplies with pull cords - one for each ensuite
price includes making safe of old electrics for walls to knocked down.
the walls are solid stone so all sockets need chasing in etc..
new consumer unit with earth of gas tank And incoming water including full test
all in ÂŁ2993,65
was I far off? I priced it like that so I would get the second part of the job which is the barn part
thoughts please would be greatly appreciated
Andy
its a barn conversion / cottage alteration and full rewire. I've priced for the cottage part as she wants it done in stages since there's a lot to do on the barn section before it's ready for electrics. Anyway apparently I've been beat on my price and I'm baffled
as followed; the cottage has 3 large bedrooms with 2 ensuites and a main bathroom , hallway stairs etc.
11 x double sockets through out
15 x chrome down lights
10 x tilt chrome down lights
7 x ip rated chrome down lights
5 x centre lights ( pendants)
each room has a 2/3 gang switch to switch lights separately
2 x mains smoke detectors
3 x timer fan installation 4 inch with isolation switches. Core holes excluded
3 x 9.5 kW shower supplies with pull cords - one for each ensuite
price includes making safe of old electrics for walls to knocked down.
the walls are solid stone so all sockets need chasing in etc..
new consumer unit with earth of gas tank And incoming water including full test
all in ÂŁ2993,65
was I far off? I priced it like that so I would get the second part of the job which is the barn part
thoughts please would be greatly appreciated
Andy