Excellent thread! Got my 302 on wednesday ferifies what I have learned in class.
With regards to the ze test being 1st, we dont get taught this in class but my tutor always performs this test 1st, as she beleive's if its done later then you have not really confirmed continuity of cpc as the main earth has been disconnected for the ze test after the continuity of protective conductors. How can ya really be sure that it has been connected back satisfactory or not least forgot to connect it back( cuppa time maybe).
With regards to the ze test being 1st, we dont get taught this in class but my tutor always performs this test 1st, as she beleive's if its done later then you have not really confirmed continuity of cpc as the main earth has been disconnected for the ze test after the continuity of protective conductors. How can ya really be sure that it has been connected back satisfactory or not least forgot to connect it back( cuppa time maybe).