P
Proper Job
Hi all
Today i was asked to have a look at an isolator that has been vandalised.The job was at a motorway service station. It has a walkway linking one station from one side of the motorway to the other which contains 12 lights along the walk way/bridge. The fused isolated is half way up one side of the ramp and has had the fuse and fuse gaurd removed ,I think it is a wilex model. We later found another isolater in a column that feeds the walkway isolater.I have switched this off hence making the walkway isolater safe.
I am assuming that the walkway isolater was put there as a type off local isolation, but I don't think it is suitable for the chosen location.
The client wants me to get these lights working ASAP. But I feel I should test the circuit before doing so which would mean opening all the lights and disconnecting what ever may be before the isotaters,and firstly finding the supply.
my question , on the walk way, remove the wilex isolater, fit a junction box housing an rcbo. Test Zs on armoured supplying walk way. Do r1 r2 test on out going lighting cable and limited insulation resistance test .
The whole things looks a mess and would prefer to stay away from it would be grateful for your help
Today i was asked to have a look at an isolator that has been vandalised.The job was at a motorway service station. It has a walkway linking one station from one side of the motorway to the other which contains 12 lights along the walk way/bridge. The fused isolated is half way up one side of the ramp and has had the fuse and fuse gaurd removed ,I think it is a wilex model. We later found another isolater in a column that feeds the walkway isolater.I have switched this off hence making the walkway isolater safe.
I am assuming that the walkway isolater was put there as a type off local isolation, but I don't think it is suitable for the chosen location.
The client wants me to get these lights working ASAP. But I feel I should test the circuit before doing so which would mean opening all the lights and disconnecting what ever may be before the isotaters,and firstly finding the supply.
my question , on the walk way, remove the wilex isolater, fit a junction box housing an rcbo. Test Zs on armoured supplying walk way. Do r1 r2 test on out going lighting cable and limited insulation resistance test .
The whole things looks a mess and would prefer to stay away from it would be grateful for your help