just after some advice for me & customer, installing immersun today through another company for someone i know.
firstly 2 years ago 6 panel system fitted, no payments at all. found that BG have had papperwork but wrong post code
so no payments over 2000 units on meter.
company now does not exist anymore & they has put down wrong postcode on job therefore no FITS.
late last year had 10 panels added to roof, company fed into same solar meter.
problem BG no that they have 6 panels on one meter at another rate. next problem the other panels need a new meter at the new rate again company does not exsit.
as they are freinds of mine would there be an issue to do all papper work for job re register job for FIT payment as it is now?
other problem solar company that installed it has not put any board behind set up straight onto brickwork & run the DC cabling in trunk with the AC supply cable. (i suppose not to much of an issue i can just remove all & do again).
anyone know how i would stand with MCS & also if i could get him the higher rate for the orignal install (i think not on the payment but maybe worth a try)??
any help would be appreciated.
just after some advice for me & customer, installing immersun today through another company for someone i know.
firstly 2 years ago 6 panel system fitted, no payments at all. found that BG have had papperwork but wrong post code
so no payments over 2000 units on meter.
company now does not exist anymore & they has put down wrong postcode on job therefore no FITS.
late last year had 10 panels added to roof, company fed into same solar meter.
problem BG no that they have 6 panels on one meter at another rate. next problem the other panels need a new meter at the new rate again company does not exsit.
as they are freinds of mine would there be an issue to do all papper work for job re register job for FIT payment as it is now?
other problem solar company that installed it has not put any board behind set up straight onto brickwork & run the DC cabling in trunk with the AC supply cable. (i suppose not to much of an issue i can just remove all & do again).
anyone know how i would stand with MCS & also if i could get him the higher rate for the orignal install (i think not on the payment but maybe worth a try)??